Session Information
ASHE 2010 International Conference and Exhibition on Health Facility Planning Design and Construction
Click here to go to the previous page
The UCSF Mission Bay Hospital - Design Assist and BIM at their Best
Track : Best Practices
Program Code: 130
Date: Monday, March 15, 2010
Time: 3:30 PM to 4:30 PM  EST
Location: SDCC — Room 31 ABC
PRIMARY SPEAKER :   Click the plus sign to see more detailed information about each speaker.
 J. Stuart Eckblad, AIA, Director of Design and Construction, UCSF, UCSF Medical Center
CO-PRESENTER (S):
Mr. J. Stuart Eckblad, AIA, Director, UCSF Medical Center
Raj Daswani, P.E., LEED, AP,, Associate Principal, ARUP
Ann Killeen
 George Pfeffer, Executive Vice President, DPR Construction
Description
As with any other project type, publicly-funded healthcare projects performed under the traditional design-bid-build contractural approach are often laden with financial and scheduling risks.

The design team generates specifications and a two or even three-dimensional set of Construction Drawings. The healthcare provider's cost estimator is able to generate a detailed cost estimate that meets the provider's budget, so the project hits the streets for bid. The contractors competing for the work not only price what is included in the Documents, but also make a mental note of what may have been unclear, in error or omitted. They ignore some of the specification requirements, deciding that their more-efficient, less-expensive materials are "industry standard" and should therefore be accepable to the owner and design team. Driven to reduce costs, the healthcare provider awards the project to the low-bidding contractor.

Throughout coordination and construction, the contractor who was awarded the work raises RFI's highlighting the Documents' confusing items, errors and omissions. These RFI's become change orders and add to those generated by the provider in an effort to keep up with ever-changing healthcare equipment technology. Submittals (sometimes) bring to light lesser materials and debates between contractor and designer ensue.

The team is rapidly approaching the scheduled completion date. There are backlogs of RFI's, submittals and change orders and the owner is signing all contractor requests to compensate for increased overtime to avoid schedule overrun.

In California, cost and schedule risks are particularly high since the government has mandated replacement or retrofit of all non-seismic-code compliant, 24-hour inpatient facilities by the year 2014. Non-compliance has serious financial consequences to the provider.

UCSF Medical Center has experienced enough of the traditional design-bid-build approach and has implemented a revolutionary design-assist approach for their new Medical Campus at Mission Bay.
The 3-dimensional CAD models generated by the design team during Design Development have been handed to the contractors. The contractors continue to detail and coordinate the major trades while the design team continues to develop the design and review the contractors' layouts. This integrated effort results in a virtual hospital Building Information Model from which Permit Documents, shop drawings and coordination drawings can be extruded, along with information regarding materials and quantities that are used to track cost metrics.

The most interesting feature of this delivery model is that most of the entire effort is being conducted within a single, large trailer on site, named the Integrated Center of Design and Construction (ICDC). Owner, architect, engineer, contractor, subcontractors, construction managers, code consultants, detailers, estimators and other members of the design and construction teams are functioning as one large team, under one large roof using state of the art CAD, BIM and visualization technologies. It is this effort, part inspired by the space industry, that UCSF Medical Center believes is the most effective means of delivering a large hospital project on time and on budget.

Although this delivery method is being tested in other medical projects, several team members have expressed their opinion that this is the best. The team members would like to share their thoughts and opinions of why this is the case and what can be done to improve this delivery method even more.

LEARNER OUTCOMES:
  • Assess whether their project would benefit from a non-traditional delivery method.
  • Identify a non-traditional project delivery method that helps ensure the financial and technical success of a healthcare project.
  • Identify potential barriers and/or hurdles to an integrated, BIM-based, design-assist delivery method.
  • Identify technologies and methods that can help a design-assist team optimize project design and coordination.


Audio Synchronized to PowerPoint
(Code: 130)
  
This session is a part of:
Handout Online
(Code: 130)
Attendee: Free
  
This session is a part of: